Schedule performance index (SPI)
The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.
As a ratio it is calculated by dividing the budgeted cost of work performed, or earned value, by the planned value.
For example:
- A project has a budgeted cost of £120,000.
- According to the schedule, 15% of the project should have been completed after one month (planned value). That is £120,000 x 15 / 100 = £18,000.
- But after a month, only 12% of the project has actually been completed (earned value). That is £120,000 x 12 / 100 = £14,400.
SPI = EV / PV = 14,400 / 18,000 = 0.8
This means that for every estimated hour of work, the project team is only completing 0.8 hours (just over 45 minutes).
If the ratio has a value higher than 1 this indicates the project is progressing well against the schedule. If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Cost performance index (CPI).
- Benchmarking.
- Design programme.
- Earned value.
- Fast-track construction.
- Key performance indicators KPI.
- Lead time.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.

















Comments
Its just 12/15 no need to multiply the percentage by the budget.
Indeed.